AAC Plant Parameters, AAC Block Machine

  • Price:

    Negotiable

  • minimum:

  • Total supply:

  • Delivery term:

    The date of payment from buyers deliver within days

  • seat:

    Anhui

  • Validity to:

    Long-term effective

  • Last update:

    2017-12-12 05:23

  • Browse the number:

    93

Send an inquiries

Company Profile

Keda (Anhui) Industrial Co., Ltd.

By certification [File Integrity]

Contact:Miss Rosa(Mr.)  

Email:

Telephone:

Area:Anhui

Address:Anhui

Website: http://keda600499.huasengtex.com/

Product details
PLANT PARAMETERS  
No. Index content unit Index value
I Name   AAC block
Production scale(annual capacity)  150,000
Specification(cake: 4.2×1.2×0.6) m China national standard(GB
II Working system(three-shift continuous weekly production)   300 days / year
22.5 hours / day
7.5 hours / shift
III Main raw material consumption    
1. sand Ton / year 65000
2.lime Ton / year 15800
3. gypsum Ton / year 2800
4.cement Ton / year 9300
IV Total capacity (without ball mill power) KW ≈630
V Annual power consumption 10,000KW.h ≈260
VI Annual water consumption Ton ≈57800
VII Annual gas consumption Ton ≈22500
VIII Single-shift producing operators  people 6
Single-shift auxiliary personnel (including forklift and boiler gas distribution ) 10
IX Total plant construction area acre ≈5.5
Construction area m2 ≈7000
Storage covering m2 ≈6000
 
 
 
 
 
 
 
 
No. Index content unit Index value
I Name   AAC block
Production scale(annual capacity)  200,000
Specification(cake: 4.8×1.2×0.6) m China national standard(GB
II Working system(three-shift continuous weekly production)   300 days / year
22.5 hours / day
7.5 hours / shift
III Main raw material consumption    
1. sand Ton / year 86600
2.lime Ton / year 21100
3. gypsum Ton / year 3800
4.cement Ton / year 12400
IV Total capacity (without ball mill power) KW ≈800
V Annual power consumption 10,000KW.h ≈320
VI Annual water consumption Ton ≈76400
VII Annual gas consumption Ton ≈30000
VIII Single-shift producing operators  people 6
Single-shift auxiliary personnel (including forklift and boiler gas distribution ) 10
IX Total plant construction area acre ≈7.5
Construction area m2 ≈7000
Storage covering m2 ≈8000
 
 
 
 
 
 
 
 
No. Index content unit Index value
I Name   AAC block
Production scale(annual capacity)  250,000
Specification(cake: 5.0×1.2×0.6) m China national standard(GB
II Working system(three-shift continuous weekly production)   300 days / year
22.5 hours / day
7.5 hours / shift
III Main raw material consumption    
1. sand Ton / year 108300
2.lime Ton / year 26300
3. gypsum Ton / year 4700
4.cement Ton / year 15500
IV Total capacity (without ball mill power) KW ≈800
V Annual power consumption 10,000KW.h ≈390
VI Annual water consumption Ton ≈94900
VII Annual gas consumption Ton ≈37500
VIII Single-shift producing operators  people 6
Single-shift auxiliary personnel (including forklift and boiler gas distribution ) 10
IX Total plant construction area acre ≈9
Construction area m2 ≈7500
Storage covering m2 ≈8500
 
 
 
No. Index content unit Index value
I Name   AAC block
Production scale(annual capacity)  300,000
Specification(cake: 6.0×1.2×0.6) m China national standard(GB
II Working system ( three-shift continuous weekly production )   300 days / year
22.5 hours / day
7.5 hours / shift
III Main raw material consumption    
1. sand Ton / year 173200
2.lime Ton / year 42100
3. gypsum Ton / year 7500
4.cement Ton / year 24800
IV Total capacity (without ball mill power) KW ≈1000
V Annual power consumption 10,000KW.h ≈500
VI Annual water consumption Ton ≈150600
VII Annual gas consumption Ton ≈60000
VIII Single-shift producing operators  people 6
Single-shift auxiliary personnel (including forklift and boiler gas distribution ) 10
IX Total plant construction area acre ≈10.5
Construction area m2 ≈10000
Storage covering m2 ≈13500
 
 
 
No. Index content unit Index value
I Name   AAC block
Production scale(annual capacity)  400,000
Specification(cake: 6.0×1.5×0.6) m China national standard(GB
II Working system ( three-shift continuous weekly production )   300 days / year
22.5 hours / day
7.5 hours / shift
III Main raw material consumption    
1. sand Ton / year 129900
2.lime Ton / year 31600
3. gypsum Ton / year 5600
4.cement Ton / year 18600
IV Total capacity (without ball mill power) KW ≈1000
V Annual power consumption 10,000KW.h ≈460
VI Annual water consumption Ton ≈113500
VII Annual gas consumption Ton ≈45000
VIII Single-shift producing operators  people 6
Single-shift auxiliary personnel (including forklift and boiler gas distribution ) 10
IX Total plant construction area acre ≈10.5
Construction area m2 ≈9200
Storage covering m2 ≈10000